Lead Times, Published

We publish our schedule. Nobody else in this category does.

DocumentLead Times
BasisPurchase order to shipment
Revision2026.1
Issued17 September 2026
Nobody in this category publishes lead times. We do, because the schedule is what actually determines when you start producing, and because the long-lead items are not the extractor. Order the ancillaries the day you order the system.
20 weeks20 LB systemPurchase order to shipment
12 weeksC1D1 boothYour build-out, not ours
20+ weeksChillerThe item that holds up most installs

N.B. OLER EQUIPMENT

Item Lead time From
20 LB Closed Loop Extractor 20 weeks Purchase order to shipment
40 LB Passive Double Barrel 26 weeks Purchase order to shipment
Vessels, columns and custom fabrication 20 to 26 weeks Quoted per build
Gaskets, clamps, fittings, valves In stock Ships immediately
Relief valves (PRVs) 1 to 2 weeks Usually on the shelf. When a setting is out, typically 1 to 2 weeks. The longest we have ever seen is 12 weeks
Onsite commissioning and training visit 2 weeks minimum Scheduling lead time once your site is ready

Expedited production is available on some builds for an additional charge. Call with your date and we will tell you honestly whether it is possible.

THE ITEMS THAT ACTUALLY HOLD YOU UP

These are not ours, and they are the ones that put a finished extractor in a crate in your warehouse for a month. Every one of them should be ordered the same week you order the system.

Item Lead time Why it matters
C1D1 booth or room build-out up to 12 weeks The system cannot be commissioned outside a rated, operational space. Permitting can add to this
Bulk LCO2 storage tank 16+ weeks At 75 L per run on a 20 LB system, a dewar will not carry a production schedule
Low-temperature chiller 20+ weeks -40 °C (-40 °F) minimum for standard cold extraction; for live resin, -60 °C (-76 °F) minimum and -70 °C (-94 °F) recommended, and 480VAC / 3Ph / 55A of service to feed it
Electrical service upgrades varies widely Get your electrician into the room before you order anything. Amperage is the most common late surprise

The sequencing mistake everyone makes

The extractor arrives before the booth is finished.

Our build takes 20 weeks. A booth takes up to 12 and a chiller takes 20 or more. Start all three clocks on the same day and they land together. Start the booth when the system ships and you have bought yourself three idle months.

A REALISTIC TIMELINE

A 20 LB system, ordered today, with everything started at once.

Week 0 Purchase order to N.B. Oler. Order the booth, the chiller or bulk LCO2 tank, and the vacuum pump the same week
Weeks 1 to 12 Booth build-out and permitting. Electrical service work
Weeks 12 to 18 Ancillaries land and get connected. Fill the dewar or tank
Week 18 Site readiness confirmed, pre-visit video call, commissioning visit booked
Week 20 System ships
Week 21 or 22 Delivery, uncrating, onsite commissioning and training begins

Training is three days minimum and five days recommended, so plan for a full week on site.

Lead times current as of September 2026 and quoted per build. Ancillary equipment lead times are supplier-dependent and outside our control, which is exactly why we publish them. Call 541-330-6409 to confirm against today's schedule.